The REGA-qualified chartered accountant’s role in a WAFI off-plan escrow account

The REGA-qualified chartered accountant reviews a WAFI escrow account’s cash flows, checks each disbursement request against the engineer-approved completion percentage, and endorses it before it goes to the bank. Entry Post CPA (SOCPA licence 933) holds REGA certificate A0565, valid until 1 July 2027.

1. Legal framework for escrow accounts and off-plan projects

Off-plan sale and lease projects in Saudi Arabia fall under a set of rules that protects buyers, developers and financing entities and limits financial and construction risk.

Governing legislation and the Royal Decree

  • The Law of Off-Plan Sale and Lease of Real Estate Projects: issued by Royal Decree No. (M/44) dated 10/03/1445H. It gives supervision of the activity and licensing of its projects to the competent authority. Article 2 of the Implementing Regulations, issued by the Real Estate General Authority (REGA), gives REGA the regulation of the activity and the issue of its licences.
  • The Implementing Regulations: issued by decision of REGA’s board of directors. They detail how licences are issued, how developers are registered, how escrow accounts are opened, managed and closed, and the roles of the parties.
  • REGA (WAFI platform) rules and instructions: the escrow account rules set standard procedures for banks and financial institutions licensed by the Saudi Central Bank (SAMA), qualified chartered accountants, and engineering consultants registered with REGA.

2. Appointing a qualified chartered accountant: who must, and when

Who must appoint the accountant?

A real estate developer, whether a natural or a legal person, who wants to sell or lease units off-plan in the Kingdom must appoint an accounting firm that holds a valid chartered accountant qualification certificate from REGA.

When to appoint

  • Stage: the accountant is appointed, the agreements are signed and the documents are completed before the off-plan licence is issued, while the escrow account application is being made to the account trustee (the bank).
  • Purpose: a qualified accountant is a basic opening condition for activating the escrow account and for REGA (WAFI) approval to start marketing, selling and receiving buyers’ money.

3. Professional scope and operating responsibilities

The qualified accountant’s control and accounting work aims to ensure that money in the escrow account is spent only on the project purposes set out in the cash flow schedule, in line with actual construction progress:

  1. 1

    Buyers and financing entities

    (deposit sales money)

  2. 2

    Escrow account at the bank

  3. 3
    • Real estate developer (submits the disbursement request and documents)
    • Qualified chartered accountant (reviews the documents, the budget and compliance with the conditions)
    • Engineering consultant (approves the technical and construction completion percentage)
  4. 4

    Account trustee (the bank)

    (approves the disbursement report)

  5. 5

    Contractors, suppliers and consultants

    (receive the transfers)

1. Reviewing disbursement requests

  • Document matching: examining the invoices, contractors’ progress certificates (mustakhlasat), completion certificates and supply contracts attached to the developer’s request.
  • Checking the approved budget: making sure the amounts requested follow the project budget lines approved in advance by WAFI and the account trustee, and that no line is exceeded.
  • Linking payment to actual progress: matching the percentage requested with the physical and engineering completion percentage approved by the project’s engineering consultant.

2. Endorsement and periodic reports to REGA

  • Frequency: under Article 15 of the Implementing Regulations, the accountant prepares and submits reports on the escrow account and its withdrawals periodically or when the authority asks. Under Article 25, REGA may request financial and technical progress reports every month for projects whose built-up area exceeds 5,000 m², projects with more than 30 units or government projects, and every three months for others.
  • Content: escrow account movement (receipts, payments, remaining balance), receipts by unit, amounts retained, and an analysis of differences between the estimated budget and actual spending.
  • Final financial report at closing: a full audited accounting report covering the whole operating period of the project, confirming that all withdrawals are complete and the rights of buyers and contractors are settled before the account is formally closed.

3. How the four parties work together

  • With the developer: confirming that deposit rules are followed, supporting documents are attached and no amount is used outside the approved route.
  • With the engineering consultant: approving financial reports on the basis of site completion reports, and confirming that costs match structural progress.
  • With the account trustee (the bank): no transfer or payment from the escrow account is released until the chartered accountant and the engineering consultancy have endorsed the disbursement document on the form approved by REGA.

4. Disbursement rules and statutory caps

The escrow rules set which expenses may be drawn from the account and the controls that protect buyers:

Expenses that may be paid from the escrow account

  • Direct construction costs: progress certificates of the main contractor and subcontractors, and building material suppliers.
  • Professional fees: the engineering consultant, the qualified chartered accountant, and engineering and survey studies.
  • Administrative, marketing and set-up costs: expenses for obtaining licences, marketing, and administrative services directly related to the project.

Caps and controls on non-construction expenses

  • Cap on marketing, administrative and set-up expenses: Article 12 of the off-plan law limits withdrawals for administrative, marketing and other non-construction expenses to 20% of the value of each unit sold. The accountant checks that total withdrawals do not exceed this percentage of the total value of units sold in the project.
  • Retention after completion: under Article 14 of the law, the accountant keeps 5% of the total construction cost in the escrow account after the completion certificate is issued, or accepts a bank guarantee from the developer for the same percentage. The amount is released one year after the project is completed, or earlier if the developer provides an insurance policy against latent defects under the Implementing Regulations.

5. The developer’s journey, from licence to account closing

An off-plan project passes through these stages on the WAFI platform:

  1. 1

    Licence issue and account opening

  2. 2

    Marketing, sale and deposits

  3. 3

    Periodic disbursement requests

  4. 4

    Completion and account closing

Stage one: preparing the file and setting up the account

  1. The developer applies through REGA’s WAFI platform.
  2. The escrow account agreement is signed between the developer and the account trustee (the bank), alongside the developer’s contracts with the qualified chartered accountant and the engineering consultant.
  3. The project’s estimated budget, construction schedule and cash flows are approved.
  4. The off-plan sale licence is issued and the escrow account is opened with the project’s own IBAN.

Stage two: deposits from buyers and marketing

  1. Sales begin and standard off-plan sale contracts are signed with buyers.
  2. All payments and instalments, whether from buyers directly or through real estate financing entities, go only to the escrow account’s dedicated IBAN.
  3. Receiving cash or transferring money to the developer’s own accounts outside the escrow account is prohibited.

Stage three: withdrawals and construction payments

  1. The developer submits the disbursement request electronically with the progress certificates for completed work.
  2. The engineering consultant inspects the project and issues the certificate of actual completion percentage.
  3. The qualified chartered accountant examines the request and checks the budget, available cover and documents.
  4. The accountant endorses the disbursement document together with the engineering consultancy, and it is sent to the account trustee to pay the beneficiaries.

Stage four: handover and closing the escrow account

  1. Construction reaches 100%, and the building occupancy certificate and safety certificates are issued.
  2. Units are subdivided and handed over to buyers, and title deeds are issued in the buyers’ names.
  3. The qualified chartered accountant submits the final financial report and settles balances and statutory retentions.
  4. The escrow account is formally closed with REGA (WAFI) approval.

6. Roles and responsibilities in the escrow system (comparison table)

PartyStatusMain role in the escrow account
Real Estate General Authority (WAFI)Regulator and supervisorRegulation, licensing, approving agreements, general oversight, and approving closing and disposal.
Real estate developerProject ownerCarries out the project, opens the account, directs receipts to it and submits documented disbursement requests.
Account trusteeBank licensed by SAMAHolds the money, makes approved transfers, and checks the signatures and approvals of the accountant and consultant.
Qualified chartered accountantSOCPA licence + REGA qualificationReviews disbursement requests and documents, submits periodic financial reports and checks that the approved budget is followed.
Engineering consultantRegistered consultancy officesInspects the project on site, reports the actual completion percentage and approves contractors’ construction progress certificates.
BuyersBeneficiaryPay amounts and instalments only into the escrow account and receive units on the agreed dates.

7. Developer obligations and documents needed for review

To keep review and disbursement on time, the developer must provide, keep and give the qualified accountant access to these documents:

Founding documents of the project

  • Title deed of the project land, or the development contract with the landowner.
  • Building approval and permits from the competent municipality.
  • A copy of the WAFI licence issued by REGA.
  • The project’s approved estimated budget and cash flow schedule.

Operating and financial contracts

  • The escrow account agreement with the account trustee and the qualified parties’ agreements.
  • Contracts with the main contractor and subcontractors, and agreements with consultancy offices.
  • The register of unit sale contracts with buyers and the instalment dates.

Disbursement request documents

  • Electronic tax invoices from suppliers and contractors, with bank proof of payment.
  • The engineering consultant’s approved certificate and statement of the completion percentage.
  • Escrow account statements from the bank, reconciled periodically.

8. Entry Post CPA services

Entry Post CPA has the experience and the set-up to provide accounting oversight and review of escrow accounts under the requirements of REGA (WAFI):

  • REGA qualification: we hold chartered accountant qualification certificate No. (A0565), valid until 1 July 2027, for off-plan sale work through the WAFI platform.
  • Professional licence: an accounting and audit firm licensed by SOCPA, No. (933).
  • All regions of the Kingdom: we serve real estate developers in Riyadh, Jeddah, the Eastern Province and all other Saudi cities and regions.
  • Review and endorsement services:
    • Examining escrow account agreements and project budgets.
    • Document and field review of disbursement requests against completion percentages.
    • Preparing and submitting the periodic financial reports and the final financial report to the WAFI platform and account trustees.

Frequently asked questions

What is an escrow account in an off-plan (WAFI) project?

It is a dedicated bank account opened in the project’s name at a bank licensed in the Kingdom. All money from buyers and financing entities is deposited in it, and it is spent only on the project, under the control of a qualified chartered accountant and an engineering consultant.

What is the legal basis for off-plan sale and lease in Saudi Arabia?

Royal Decree No. (M/44) dated 10/03/1445H, and its Implementing Regulations issued by REGA’s board of directors.

Can the developer receive sale payments in its own business account?

No. The developer is prohibited from receiving any payment in cash or through its own accounts. All receipts and instalments must go to the IBAN of the project’s approved escrow account.

Why is a REGA-qualified chartered accountant important?

The qualified accountant protects deposited money, verifies that expenses are properly documented and compliant, and matches costs with the budget and licences before any transfer from the account is approved.

How are payments to contractors calculated?

They are based on the progress certificate for completed work, approved by the engineering consultant and applied to the actual completion percentage, after the qualified accountant has reviewed the documents and invoices.

What is the cap on non-construction expenses from the escrow account?

Article 12 of the law caps non-construction expenses, such as marketing and administration, at 20% of the value of each unit sold. The accountant checks that the overall total does not exceed this percentage of total sales.

What is the 5% retention and when is it released?

The accountant keeps 5% of the total construction cost in the escrow account after the completion certificate is issued (or the developer provides an equal bank guarantee). It is released one year after project completion, or once an approved insurance policy against latent defects is provided.

What does REGA do in supervising the account?

REGA licenses the project, registers developers and qualified parties, receives the accountant’s periodic reports, and gives final approval to settle and close the escrow account.

What does the engineering consultant do when money is paid from escrow?

The consultant inspects the site, checks the technical progress certificates and issues the official certificates of the project’s structural and construction completion percentage.

Are qualified accountants’ services available in all regions of the Kingdom?

Yes. Qualified professional firms with digital systems review and oversee escrow accounts for real estate projects in all Saudi cities and regions.