Contractor claims: the financial side We rebuild the project ledger; the engineer covers quantities and delay
For a contractor whose certificates are unpaid, an owner facing a claim whose figures are in doubt, or a subcontractor waiting for a final account.

The short answer
A construction dispute has two halves: engineering (quantities, quality, delay) and financial (what was certified, paid, deducted and spent). We take the financial half, tying each certificate to its payment, deduction and cost in one ledger, and work with an engineer on the engineering half. We give no opinion on the length or cause of delay.
Official sources: Bureau of Experts: Law of Evidence, M/43 (Arabic) ↗Umm Al-Qura gazette: Procedural Guides to the Law of Evidence (Arabic) ↗Ministry of Justice: Arbitration Law, M/34 (Arabic) ↗SOCPA: consulting standard, engagements to provide forensic accounting services (Arabic) ↗

Engineer or accountant? Who handles a disputed project final account?
Often both. Entry Post CPA (إنتري بوست), licensed by SOCPA (No. 933) in Riyadh and working in every region of the Kingdom, handles the project’s financial account (محاسبة قضائية) for a contractor, owner or subcontractor: certificates, advances, retentions, deductions and actual cost. It works with an engineer on quantities and delay. The output is a documented project statement with schedules; it is party-side work; what a court or tribunal directs is taken in another case, subject to the signing expert meeting the licence and listing requirement. The firm is registered on the Ministry of Justice’s Khibrah platform, registered and qualified with the Infath center, and has issued expert reports whose details are not published. To request it, use the form on this page.
Illustrative example: what is left to pay?
Hypothetical figures in SAR, excluding VAT.
- Work certified:
- 10,000,000
- Retentions:
- (1,000,000)
- Recovery of the advance payment:
- (1,500,000)
- Paid through the bank:
- (6,900,000)
- Outstanding before deductions:
- 600,000
- Deductions in dispute:
- (250,000), leaving 350,000 not in dispute
The 1,000,000 of retentions is a separate item, due on its own contract terms.
What do we examine?
Certificates
Submitted, certified and paid, with reasons for reductions and dates.
Deductions and penalties
Each deduction’s amount and the contract term or letter behind it, without ruling on its legal validity.
Actual cost
Project cost from payroll, materials and plant, and its share of overheads on one basis.
Variations
Billed and unbilled variations, tied to a quantity the engineer confirms.
What is certified, paid and disputed?
Give us the project, the contract parties and your date; we start with the conflict check.
What helps before and during a case?
- 1
Preserving the state of things
The Law of Evidence allows an urgent suit to record a state of affairs at risk of being lost (Article 109/2); your lawyer decides on it.
- 2
Expert work agreed before filing
If both sides agree it before filing, the report is filed with the claim and treated as a lodged final report (Procedural Guides, Article 110/3), and the expert must be licensed (110/2).
- 3
More than one expert
Several experts give one report showing where they differ (Law of Evidence, Article 117).
- 4
Arbitration
Parties supply the tribunal’s expert with information, and the tribunal settles disputes about it (Arbitration Law, Article 36).
Which documents do we start with?
- The contract, bill of quantities, variation orders and certified payment applications.
- Bank statements for receipts and the register of guarantees and retentions.
- The project cost ledger, payroll and purchases.
- The engineer’s report if issued, and letters with a financial effect.
We take them after the conflict check. Delivery is set to the hearing or contractual reply date with a team to match the project, and we commit to a date only when sure it can be met.
When do you need someone else?
- If only delay, quality or quantity is in dispute: an engineer.
- If the question is contract meaning or valid termination: a lawyer.
- If the conflict and independence check done before acceptance rules it out: another firm.
Frequently asked questions
A contractor claims on incorrect certificates. Who checks them?
An engineer checks quantity and quality; we check pricing, arithmetic, payments, deductions and whether an item has been paid before.
The owner deducted penalties. How do I show what I am owed?
We prepare a statement splitting certified, paid and each deduction with its basis, so the agreed amount stands apart from the disputed one. Whether the penalty is valid is for your lawyer and the court.
Do you calculate delay costs?
We work out actual cost for a period the engineer sets, such as site, plant and payroll. The length of the delay and who is responsible are not ours to state.
Can the statement be used to negotiate without a case?
Yes. A statement separating agreed from disputed items lets the talks start on the difference alone.
How do you work with the engineer?
We agree in writing who covers what: the engineer signs quantities and time, we sign the figures built on them, and each report states what it relies on. In work directed by the litigation body another expert is used only with its consent (SOCPA standard, paragraph 36).
Official sources
- Bureau of Experts: Law of Evidence, M/43 (Arabic)
- Umm Al-Qura gazette: Procedural Guides to the Law of Evidence (Arabic)
- Ministry of Justice: Arbitration Law, M/34 (Arabic)
- SOCPA: consulting standard, engagements to provide forensic accounting services (Arabic)
General information from the official sources listed, as read on 23 November 2026. It is not legal or Sharia advice; ask your lawyer about your case.